Puerto del Callao-South Quay Port of Export

The most important of Callao. It started operations in May 2010. It is a unique container pier with a length of 650 meters and a depth of 16 meters, so you can receive large container ships Post Panamax type.

has two berths of 300 meters long, each equipped with three quay gantry cranes. Also, a large patio container, in which they operate TRG cranes eighteen (yard). It also has all the infrastructure of a modern spring.



In its second phase, which start to be built when demand requires it, extend its length by 300 meters, up to 950, and incorporate other three quay cranes and nine patio.
was built by the consortium CBD Callao (led by the Brazilian company Odebrecht), on behalf of the concessionaire company Dubai Ports World Callao, operator of the dock.